From 27 November, builders and designers may only use the most recent version of compliance documents to comply with the energy efficiency requirements of clause H1 in the Building Code. Up until now, designers had the option to use the previous version

The changes follow a review of H1 in 2024, which identified opportunities to better balance upfront building costs and longer-term benefits.

The transition period ends on 26 November. From 27 November 2026, builders and designers will no longer be able to use the Schedule method as a compliance option for Building Code clause H1.3.1(a). This leaves the Calculation method and Modelling method as the two ‘deemed to comply’ pathways for H1.

MBIE said via its Codewords article that “licensed building practitioners who have fully relied on the Schedule method will need to upskill on using the Calculation method and may wish to make use of the free online tools available through BRANZ or the New Zealand Green Building Council.”

Designers and architects with access to specialised modelling software can continue to use the Modelling method to meet the requirements of H1/VM1 or H1/VM2.

When Building and Construction Minister Chris Penk announced the changes in July 2025, New Zealand Certified Builders chief executive Malcolm Fleming was quick to show his support.

Fleming said the removal of the “blunt instrument” that was the Schedule method was good news and demonstrated the minister was listening to the industry.

Changes to windows, floors and heated surfaces

MBIE has also adjusted the Calculation method to provide greater flexibility in how insulation is distributed across a building. Under H1/AS1, the minimum construction R-value for slab-on-ground floors has been removed, while H1/AS2 removes the minimum construction R-values for roofs and floors.

Despite these changes, MBIE said the overall level of energy efficiency and insulation required remains unchanged.

MBIE has also updated the performance tables for windows and doors in housing and expanded the calculation tables for slab-on-ground floors to cover a wider range of building designs.

The changes to slab-on-ground floors include provisions for buildings with different cladding types and those where slab-edge insulation does not extend around the entire floor perimeter.

The requirements for heated floors, walls and ceilings have also been clarified. Special minimum construction R-values do not apply where these elements are heated solely in rooms containing a shower, bath or toilet.

Additionally, thermal bridging from wall framing must be more adequately considered. From 27 November, designers must assume a minimum framing percentage of 38%, unless they can show a lower percentage is justified.

Insulation performance remains important

While MBIE has reduced some minimum R-values, the Insulation Association of New Zealand (IAONZ) has emphasised the importance of ensuring insulation installed on site delivers the performance specified during design.

An article published by IAONZ, following the appearance of its president Nick Hall on the Building Pulse podcast, pointed out the importance of ensuring installed insulation matches the design specifications.

“It is not enough to specify the right R-value. We need confidence that the insulation actually installed delivers the performance the building was designed to achieve,” the article stated.

IAONZ identified product substitution, gaps, compression, thermal bridging and poor installation detailing as factors that can compromise thermal performance.

The association has also promoted its Prove the R initiative, which encourages builders and installers to retain evidence of the products installed, including photographs, product identification and installer declarations.

Other changes to H1 compliance

The updated H1 documents clarify how roof, wall and floor areas must be measured, requiring designers to use overall internal dimensions, including the thickness of internal partitions.

The Calculation method also limits glazing to 40% of gross wall area.

The revised H1/VM1 and H1/VM2 verification methods include changes to modelling requirements to better reflect modern building practices.

The updated H1 Acceptable Solutions also reference MBIE’s Building Product Specifications when determining the thermal resistance of insulation materials, replacing direct references to AS/NZS 4859.1.