Home News Industry Updates It’s time to talk about consents

Issue 56 – September 2016

It’s time to talk about consents

26 Aug 2016, Industry Updates

Local government bodies are an easy target when things start to go awry and the building consent process is no exception – so we decided to get their side of the story

Every day, staff at New Zealand’s 72 accredited building consent authorities (BCAs) work hard issuing consents for all sorts of building projects, ranging from multi-storey bespoke homes to retaining walls and carports. 

Legislation requires that these consents be processed within 20 working days. Under Construction canvassed a selection of BCAs to find out how many consents they’re processing within that statutory period and to provide a snapshot of how well authorities are performing nationwide.

The legislation allows for BCAs to ‘stop the clock’ when they need to request more information from the applicant, which means that a consent classified as processed within the 20-day statutory period may actually have taken longer than that to process.

Eight BCAs provided figures of how many consents they processed within the 20-day limit for the year to June 2016. Of those, seven consistently processed more than 90% of all building consents within the limit.

The top three performers were Upper Hutt City Council and New Plymouth District Council (both 100% within the limit) and Tasman District Council (98.6% within the limit).

What causes delays?

Building control officers across the country cited incomplete documentation as the most common cause of delays in the consent process.

Tasman District Council building assurance manager Sharon Threadwell said that while her department was performing well, she estimated around 80% of all consent applications required ‘stop the clock’ information requests.

Sharon’s advice for builders and designers submitting consent applications is to:

  • Attach a covering letter outlining what’s included in response to further information requests, to reduce time.
  • Apply for a project information memorandum (PIM) before applying for a building consent, because the two don’t need to be applied for together.
  • Ensure that the plans and specifications in the application meet the minimum standards required by the building code. 

“I think what often happens is that a client might get on a builder or designer’s case, so they end up submitting incomplete forms to be able to say a project is under way – but a clean consent leads to a faster consenting process, which is better for everyone.”

New Zealand’s largest BCA, Auckland Council, processed more than 20,000 building consents between June 2015 and May 2016 and, on average, more than 96% were processed within the 20-day period.

Building control manager Ian McCormick said that around 68% of those required additional information requests.

“Every time we have to request additional information, it slows everything down because often we’re waiting up to a week or longer for the information to be provided. Then the processing officer has to review all the information again to remind themselves of what they looked at previously,” said Ian.

He listed common problems leading to further information requests as:

  • Design plans submitted without enough information.
  • A lack of coordination between experts, such as engineers and architects.
  • Designs that don’t take building site features into account.

“As general advice, I’d recommend that designers visit a site before submitting any plans to us and also that people approach us with any questions as early as possible.

“We’re very open to having conversations to help smooth out the process.”

Quality control

Head of building consents at Christchurch City Council (CCC), Leonie Rae, said that some builders and designers treat councils as their quality assurance provider.

“There seems to be a mindset among some people that they’ll just put an application into council and let us determine what’s missing, rather than actually submitting a complete application up front,” said Leonie.

“So, with inspections for instance, we’ve started sending some of our group home builder customers reports highlighting their inspection failure rates and how much that costs them in dollar terms.”

One of the CCC’s customers had a failure rate of around 50%, which has since dropped to close to 20% because they introduced a quality assurance system. Leonie said she recommends all building companies put in place their own quality assurance systems.

“At the end of the day, we’re talking about building houses. We want to work with the industry to make sure we have quality housing stock for the future and I think builders and designers with robust quality assurance systems play a part in that.”

Don’t be afraid to pick up the phone

New Plymouth District Council building lead Peter Scantlebury agrees with the sentiment that a number of people within the industry rely on councils as their quality control.

Peter – and the others quoted in this article – said that hosting good conversations with the building industry was a positive way of addressing the issue.   

“We send out a newsletter every two months to designers and builders, and every three months we hold a group meeting with industry practitioners and the professional groups (RMB, CBA etc), so we can address any issues.

“I find that by having a working relationship with our stakeholders, you tend to get more willing compliance rather than if you’re seen as a monster on the other side of a desk.”

Peter said that while they couldn’t force people to attend the meetings, they were always open to answering any questions builders may have about a consent or building legislation in general.

An ageing workforce

While there are a number of things that those in the construction industry can do better to speed up the consenting process, it’s widely acknowledged by council building managers that one of the biggest challenges they face is attracting quality inspectors and processors to their departments.

Upper Hutt City Council’s director of planning and regulatory services, Richard Harbord, said as demand has increased on councils, recruiting has become more difficult. 

“There is a shortage of qualified building officers, so it’s quite hard to recruit,” said Richard.

“The job requires a high level of industry knowledge and a wide range of skills, so attracting and training new people isn’t simple.”

The average age of workers in New Zealand’s local government building departments was estimated
at around 55, which Richard said put more pressure on councils as older workers would need replacing as they retire. 

Ian McCormick said that one of the ways Auckland Council is encouraging people to join its building department is by offering staff the opportunity to upskill.

“We’re trying to position ourselves as a place where you can become an expert in the building industry and we’re beginning to attract younger, more ambitious applicants, because people are beginning to recognise the investment we’re making in them,” he said.

“We also run a fast-track school, which is a six-week intensive training course for processors and inspectors that we run every two months or so.

“We’re putting a lot of resource into making the industry more professional, because there is actually a lot relying on our practitioners’ expertise.”

Next month we’ll look at some of the programmes and initiatives councils are working on to make the building consent and inspection process more efficient.


Register to earn LBP Points Sign in

Leave a Reply